Variances
Submitted by elthox on Sat, 07/06/2013 - 18:24
Hi,
What number tells you the difference between the amount of money you planned on spending and what you`ve actually spent so far on the project?
A. AC
B. SV
C. CV
D. VAC
Forums:


vijayavadrevu
Mon, 07/08/2013 - 11:17
Permalink
It should be C
It should be C
cnppmp1
Thu, 07/11/2013 - 15:07
Permalink
B
It should be SV, as it is talking about planned value and other value should be consdiered as EV is actually accomplished value.
Regards
CN Patil