Severe Variance
Submitted by ppalkonda1975 on Fri, 07/19/2013 - 02:25
| You have recently taken over a new project. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, what should you recommend? |
||
| Choice 1 | Issue budget updates | |
| Choice 2 | Revise the cost baseline | |
| Choice 3 | Adjust schedule activity budget | |
| Choice 4 | Close the project | |
Forums:


pmpnewster
Fri, 07/19/2013 - 02:34
Permalink
Choice 2.Cost Baseline needs
Choice 2.
Cost Baseline needs to be revised. Most likely the original estimate was flawed.
Regards.
vikula01
Fri, 07/19/2013 - 02:36
Permalink
is it choice 2 ?
I am not sure about it but when cost variance is severe there can be two reasons - poor planning or more changes - so I guess choice 2 might be right -
Please let me know
ppalkonda1975
Fri, 07/19/2013 - 02:37
Permalink
choice 2 is correct...but i
choice 2 is correct...but i have a question...if project sometimes is in extremely bad state then we should close the project and start fresh ...isnt it?
vikula01
Fri, 07/19/2013 - 02:44
Permalink
real basis is the catch word i believe
The question didn't say that project is in bad shape - it said CV is high and what should we do to get the real performance - so its a hint that something is not right - yes we close the project if its in bad shape but not in this case I believe -
ppalkonda1975
Fri, 07/19/2013 - 02:47
Permalink
I went with the word
I went with the word "Severe" which meant extreme case for me and that's why i am confused....