Opportunity Cost
Submitted by elthox on Fri, 07/19/2013 - 16:21
| Which of the following projects described below will you select? |
||
| Choice 1 | Project A with opportunity cost of $ 100,000 and investment of $ 1,000,000. | |
| Choice 2 | Project B with opportunity cost of $ 200,000 and investment of $ 500,000. | |
| Choice 3 | Project C with opportunity cost of $ 300,000 and investment of $ 3,500,000. | |
| Choice 4 | Cannot be determined from the above options. | |
Forums:


vikula01
Fri, 07/19/2013 - 16:25
Permalink
choice 1
We don't know anything else apart from investment - so based on opportunity cost I will go with choice 1 - the one with less OC .
pmpnewster
Fri, 07/19/2013 - 16:30
Permalink
Choice 4. Regards.
Choice 4.
Regards.
cnppmp1
Sat, 07/20/2013 - 10:16
Permalink
A
always low opportunity cost to be selected..and it is A, which has $100,000
Regards
CN Patil
ppalkonda1975
Sun, 07/21/2013 - 00:27
Permalink
choice 4 as enough info is
choice 4 as enough info is not present
vmetha
Sun, 07/21/2013 - 02:15
Permalink
4
Project are selected based on investment. Opportunity cost is project cost that you give up and it just project $ value you won't be doing. Project selection is based on the factors of investment, which is not clear here so would go for option 4.
elthox
Sun, 07/21/2013 - 14:52
Permalink
As per test authors Correct
As per test authors Correct answer was 4