Question about changes
Question:
You are completing the work defined in the project scope statement of a new software development project when a team member points out that you have an opportunity to deliver enhanced capability to the client at no extra cost, time, or risk to the project.
What should you do next?
Choices:
A. Assess the change through the change control process and, if approved, amend the project scope statement.
B. Decline to make the changes and proceed to deliver exactly what the scope statement sets out.
C. Make the changes and surprise the client with the extra capability.
D. Ask the team member to keep quiet about the changes and ignore his request because it presents too many risks to the project.


sheeraz
Fri, 08/30/2013 - 20:03
Permalink
Apropriate Seems Answer B
As the project is ending and the project manager should be smart enought to evaluate the change. and Decline to make the changes..
ppalkonda1975
Fri, 08/30/2013 - 21:36
Permalink
It is B as gold plating
It is B as gold plating should not be allowed in the project and the scenario talks abt gold plating
antonyvd
Sat, 08/31/2013 - 09:48
Permalink
Gold plating
The answer is 'B' .If we are adding extra features to the product that is not mentioned in the project scope statement it will become gold plating and is prohibited as per PMI.
GSA
Sat, 08/31/2013 - 11:23
Permalink
Answer is A according to the author
Thanks for the feedback. A is the answer according to the author.
Below is his explanation:
This is an issue about "gold plating," which, in effect, means you are delivering more than what you were required to do. Although this sounds like a good thing to do, it also means you are not delivering what has been documented. There are no problems with seizing the opportunity to deliver more, but you must always be delivering what is agreed and documented. Therefore, in this case, you would formally assess the change; if your change control process accepts it, you would then amend the necessary documents so that at all times you are delivering exactly what is documented.
If you can assess the request and approve it through your approved change control process, there is no reason simply to decline it. You should always look for ways to deliver more than what was expected as long as it is documented.
The first step before making the changes and surprising the client with the extra capability is to assess the change through your change control process.
If you can assess the request and approve it through your approved change control process, there is no reason simply to decline it. You should always look for ways to deliver more than what was expected as long as it is documented.
Bart
Sat, 08/31/2013 - 14:38
Permalink
Working backwards
Focused2013
Tue, 09/03/2013 - 11:13
Permalink
Key point
The key point here is that it was run through the change control board which would have analyzed the impact on scope, schedule, and budget. I agree it does fall under gold plating.