Preventative vs corrective actions

 Hi,

can someone pleae explain why the answer is A and not C. 

You have identified a negative risk within your project and would like to implement a word-around to the risk. A work-around is an example of:

A. Corrective action

B. Defect repair

C. Preventative action

D. WBS issue

 

Thanks

 Dear Friend,

       If you stress on the keyword "Work Around". In the current questions the users has already identified the negative risk. The option C is not correct becuase here user is asking us Work around and thats ia corresponding to Corrective action and not preventive. If he did not stress on teh word Work around then C would be the correct answer.

Dear Friend,

  Try to Stress on keywords, thats easy for us to pick the best answer.

 

Regards,

Vishwanath