Oliver lehmann (75Q) lead lag question
Submitted by danielkoshy on Sat, 02/22/2014 - 18:26
hello all
Could someone please help me understand this question.
| Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B? |
||
| 36 days | ||
| 37 days | ||
| 39 days | ||
| 42 days | ||
answer is b) 37 days.
Forums:



danielkoshy
Sat, 02/22/2014 - 19:38
Permalink
I found it
Hello All
I got the answer it was in another post called 'duration'. clearly explained by robleis. My concept of leads and lags is crystal clear now.
admin
Mon, 02/24/2014 - 05:31
Permalink
Already asked few times on
Already asked few times on pmzilla. Check this http://pmzilla.com/activity-duration-calculation