To whom is the project manager MOST accountable?
Submitted by Jp2786 on Tue, 05/27/2014 - 02:33
Senior management has imposed a project delivery date prior to the acceptance of
project scope statement. To whom is the project manager MOST accountable?
a) Project sponsor
b) Project team
c) Customer
d) Senior Management
Pls let us know the rational for chossing a particular answer?
Forums:


admin
Tue, 05/27/2014 - 03:52
Permalink
PM is accountable to Sponsor
PM is accountable to Sponsor and Sponsor will be accountable to Clients.
sunku65
Tue, 05/27/2014 - 14:28
Permalink
PM is accountable to whome
PM is accountable to whome sign the Project charter and who appoint him in the project and gave the authority. All that in the Project Charter. Here, Project Sponsor is the default one.
keyveeyen
Tue, 05/27/2014 - 17:47
Permalink
The Answer is C
the project manager must facilitate a fair and equitable solution, but the CUSTOMER is the first of equals.
Jp2786
Tue, 05/27/2014 - 17:54
Permalink
Customer
I too went with sponosor but the answer guide says customer....