Uncontrollable risk
Submitted by yatinc on Tue, 06/17/2014 - 03:00
Which of the following risks may be an uncontrollable risk?
A.
Excessive change orders
B.
Workmanship errors
C.
Material costs
D.
Scope growth
Can somebody let me know why the answer is C.
My guess was D
Forums:


admin
Tue, 06/17/2014 - 04:11
Permalink
Material cost is driven by
Material cost is driven by market and not directly within the control of project manager or project management team. Its and external factor and hence cannot be controlled by PM.
yatinc
Tue, 06/17/2014 - 06:15
Permalink
Thanks admin. I was just
Thanks admin. I was just thinking the sponser can increase budget, increase scope and can extend the project time line as well, for which the PM just cannot deny.