Work Performance Data vs Information
A project team has recently computed the project's current schedule and cost performance indices. They have also calculated the new estimate to complete and the TCPI based on the new estimate at completion. The project key stakeholders are not fully aware of the earned value management process. These measures in this case are an example of?
A.Work performance data
B.Lessons learned
C.Work performance information
D.Learning curve for the stakeholders
The answer is A
But my doubt is because schedule cost performance indices and TCPI are calculated from the work performance data and are wok performance information.


Nabs
Sun, 06/22/2014 - 12:23
Permalink
since the stakeholder are not
since the stakeholder are not aware of earned value management technique and they don't understand the data you are presenting them so it is out of context meaningless info for them.
work performance information is meaningful and provide sound foundation for project decision.
this is my opinion. would appreciate others opinion.
what is the source of this question?
chullan88
Sun, 06/22/2014 - 13:24
Permalink
Scordo
Scordo
I dont remember the Lite Mock Exam NO.
chullan88
Sun, 06/22/2014 - 13:24
Permalink
Scordo
Scordo
I dont remember the Lite Mock Exam NO.
PMP Fighter
Sun, 06/22/2014 - 14:30
Permalink
I suppose the stake holder is
I suppose the stake holder is project team member which in executing the project.
This question maybe asking the stage in Monitoring and controlling.
Imagine project manager meeting with team members, so the input is Work performance data ,which is output on direct and Manage Project Work, use for discuss the progress, address the problem etc.
And finally output the Work performance information on control stakeholder engagement process.
Correct me if i am wrong.
I am not sure the answer too.
sunku65
Mon, 06/23/2014 - 16:24
Permalink
The project key stakeholders
The project key stakeholders are not fully aware of the earned value management process. These measures in this case are an example of?
Read it again above. The stakeholders are not fully aware of the EVM process.
These measures are from Work Performance Data. The stakeholders are not taking about TCPI and ETC.