CHANGE WORKFLOW. Is that correct?
After reviewing several q&a regarding this topic i came with this detailed workflow.
I would like to check with you if it's correct and detailed.
1.- Receive FORMAL request of change from stakeholder. (Some questions tell you that the request is informal, so you have to make the customer to send a formal request).
2.- EVALUATE the impact, regarding scope, time, cost, quality, risk, Resources... (anything else here?).
3.- INFORM the stakeholder regarding the impact of the change.
4.- Send the request to CHANGE COMITE BOARD and/or SPONSOR
5.- Implement the APPROVED change.
Is this correct?. Any other thoughs?
Regards,


admin
Wed, 03/12/2014 - 06:44
Permalink
Yes its correct. Also read
Yes its correct. Also read this
http://pmzilla.com/pmp-question-change-request-processing-sequence
http://pmzilla.com/correct-order-submitting-change-request
Swapnyl
Wed, 03/12/2014 - 07:09
Permalink
workflow is correct
1. Any communication with a PM has to be formal in a project unless it is from a team member
2. for point 4. it is Change Control Board CCB that approves all the CRs.
interservicio
Wed, 03/12/2014 - 08:18
Permalink
Thanks both of you ¡
Thanks both of you ¡
Sandy10001
Thu, 07/31/2014 - 01:29
Permalink
Change Control Procedure
You are close to a good format. I would edit as follows:
1.- Receive FORMAL request of change from stakeholder. (In PMI-land there can't be an 'informal' request for change).
2.- DOCUMENT the request in the CHANGE LOG.
3.- CONVENE and SUBMIT the request to the Change Control Board.
3.- EVALUATE the impact, regarding scope, time, cost, quality, risk, Resources... (simply put, any component of the project that could be affected by the change should be reviewed).
4.- UPDATE the PMP, CHANGE LOG, and any other relevant project documents.
5.- INFORM relevant stakeholders (team, customer, sponsor, etc) of the impact of the change.
6.- Implement the APPROVED change.
Feel free to contact me for more information. I teach for PMstudy.com and cover this thoroughly in class.