What is the ROM?

 


I am confused as some books say it is +/-50% others say it is -25/+100. Does anyone have a definitive answer?


 


 

I will trust PMBOK guide and remember that.



Cost estimate is an iterative process. ROM (rough order of magnitude) is in range of +/- 50 % in initiation phase ( at start of project).This means estimate is very rough.

However when details are provided during project execution then this ROM could narrow down to +/- 10%.This means estimate is getting corrected and going towards actual.

If no information is provided on project phase then it is taken as +/- 50%.

Regards
Akshay Singh
akshay@emensuslearning.com
www.emensuslearning.com

It is rough order of magnitude estimate and is -25% to +75% accuracy for the exam.