4500 hours = projects from last 2 years(572) business days or 3 years
Hello,
Firs of all many thanks for this very informative knowledge hub.
I want to ask this question as in how to mention the 4500 hours?
I have around 5+ years experience however I'm around 2+ years in current Organization. When I calculate the business days it comes out as around 572 withing last 2 years itself. So my question is:-
-> As 2 years = 572 business days = 4500+ hours already.
Should I mention the projects only from current organization or should include projects from earlier organization also. This might make effect over the PMI Application Processing. Would that be considered better to mention projects from earlier organization also and forward the contacts for both Orgs?
Thanks!


admin
Fri, 10/10/2014 - 05:30
Permalink
You can include all the hours
You can include all the hours that you have spent on Project management. Just make sure if audited you can provide the evidence in terms of letter from your previous company.
amitthk
Fri, 10/10/2014 - 06:26
Permalink
Thank you!
Thanks a lot for your reply Admin. Just a small follow up query please:-
So this means minimum should be 4500 hrs and more can be included. And, Letter as in experience letter might not be sufficient right? Or would that be something like signing on the excel sheet mentioning exact hours in process groups?
I will be providing my earlier manager's contact.
Thanks again & have a great day!