Cost

 Hi

this is question in Cost section of Rita's book for CAMP. the answer is mark as "D" but i think it should be "A". Can you please confirm it?

Question: if the team is using performance measurement analysis and variance analysis, they are performing:

a) cost control

b) qualitative risk analysis

c) dependency determination

d) cost budgeting

 

Thanks

Al

Aslong he mentioned variance this meaning something related to monitoring and controlling