Requirements VS Deliverables
Submitted by Sam82 on Wed, 05/27/2015 - 08:54
Dears,
I was wondering in which stage we link our requirements to deliverables to meet them, is it in the "collect requirements process" or in "Define scope process"?
Note: the requirements and the link to the deliverables and to the objectives are documented in the requirements traceability matrix.
Forums:


admin
Wed, 05/27/2015 - 11:47
Permalink
when you goto next level of
when you goto next level of details, which is after you have collected the requirements.
Sam82
Wed, 05/27/2015 - 13:30
Permalink
Dear Admin,
Dear Admin,
Thank you for answering, my question is in which process this will happen in collect requirements or define scope ?
jyotig
Thu, 05/28/2015 - 07:38
Permalink
Define Scope
In Define Scope :)
Sam82
Sat, 05/30/2015 - 15:35
Permalink
Great,
Great,
thank you all for support.