Question: PM needs to focus on his / her project first.

You are the project manager of a critical project in the manufacturing area.  This project has very high visibility and cannot slip the target completion date.  Senior management asked you to help other project manager in the supply chain as well since you are the most experienced PM in the organization.  What will help you BEST to keep focus and quality at the level required that becomes integrated part of the project management plan of the manufacturing project in this scenario:

1.  Cost baseline
2.  Schedule baseline
3.  Quality Responsibility
4.  Scope baseline

 I would say answer is D: Scope baseline.

Reason: Scope baseline is input for cost baseline, quality plan, and schedule baseline.

Good luck.

RP, PMP

Find more sample questions and answers at www.mypmpexamprep.com

 

.

yes scope baseline