The Project Charter
Submitted by DaveLitten on Tue, 07/12/2011 - 07:58
The Project Charter is the “trigger” that formally starts the project, and as such is a vital and important document- the project cannot be started without one!
The Project Charter officially recognizes and authorizes that the project exists - without one, there is no project. It authorizes the project to begin, the project manager to assign resources to the project, and to spend money!
It provides the high-level requirements for the project, and links the project to the ongoing work of the organization.It is the target for the project, and a definition of how success will be measured.
The Project Charter documents the Business Need and justification, and describes the customer’s requirements.
A key input to the creation of the Project Charter is the Statement of Work (SOW), and this describes the product or service that the project was undertaken to complete – usually written by the Sponsor or the Buyer...
It is important for the PMP exam for you to know the following:
The Project Charter is created in the initiating process group
The Sponsor issues the Project Charter, and is written in broad terms so that it would normally not need to change throughout the project. If any such change is requested,then it is likely that the project should not continue.
It is important that you do not confuse the project charter with the project management plan (which is far more detailed).
So What is included in a project charter?
Project Title and Description
This describes the reason and purpose of the project.
Is it fixing a problem or gaining an advantage?
The Project Manager and assigned authority level
Fairly obvious, name the project manager, and also describe what authorities they have, for example setting budgets or timeframes within the project and authorizing changes
Business Need
This answers the question "WHY is this project being carried out" from the perspective of the business,
and could describe how it either/or reduces pain or increases some form of gain.
Project Justification
This is the financial justification, and would include a high level dewcription of financial benefits.
Resources pre-assigned
The name and number of resources that are already in place along with the reason for this.
Stakeholders
Naming those who will either affect or be affected by the project
Stakeholder Requirements
This will often be an attachement in the form of a requirements or specification document.
Product Description/Deliverables
This will detail the products that are to be created (not the activities!), and the main outcomes/end deliverable of the project.
Wherever possible this should include the quality criteria for each product, or if this is not known yet, then the individuals responsible for determining such criteria
Constraints and assumptions
A constraint is a limiting factor that the project must work within, it may be time, cost, quality, or even the
need to comply with some process or procedure. All projects will have constraints.
An assumption is a statement which you believe at this time to be true. Assumptions should be continually checked, because if they are wrong, they are likely to impact the project in some way. Assumptions could be seen as risks.
For More information check out my PMP PRIMER
Forums:


javedpmp
Wed, 07/13/2011 - 12:08
Permalink
PROJECT CHARTER
sankalp.navghare
Fri, 07/04/2014 - 06:14
Permalink
Does Dave Litten's PM Primer qualify for 35 hrs of PM education?
Hi Dave,
I am amazed with your You Tube Videos. Especially the Microsoft Project in 16 Mins. falt & Earned Value Management
I am about to buy your PM Primer but
Does PM Primer qualify for 35 hours of PM education?
Is PM Primer an REP of PMI?
I enquired at PMI chapter in my city, and they said that you shall have to have 35 education hours certificate to attempt the PMP?
Looking forward to your reply
Regards,
Sankalp