Difference between Project Calendar and Resource Calendar

Hi


I'm not clear with the following:


1) Difference between Project Calendar and Resource Calendar


2) If suppose that in the fixed price contract, - while calculating PTA (Point of Total Assumption) suppose that the ceiling price is not given then which amount to take for calculation?


My advance Thanks,


Sankara


 


 


 

admin's picture

Resource calendar show the availability of resources during the course of project. Can be people or hardware. Once you know the availablity you can do accurate estimations and planning.

Project calendar simply shows the list of working and non working days either holidays or planned time outs when the scheduled work activity will not be done or idle time of the project

As for your question on PTA , by definition if you want to calculate PTA , ceiling price must be known. I dont think you can make an assumption of ceiling price.