Help with simplilearn questions
Q1. A project team is in the planning stage and they have completed creating Work breakdown structure for the project. Which of the following process can they start NEXT?
A. Define Activity B. Estimate Cost C. Determine Budget D. All of the above
Q2. A project manager is in the process of analyzing activity sequences, durations, resources requirements and schedule constraints to create an approved project schedule. What should he do NEXT?
A. Determine Resource Requirement for each activity in the project
B. Use techniques like Critical Path method, What-if Analysis to calculate optimum duration of the project
C. Use this approved schedule duration as baseline and start tracking the project
D. Create a Network diagram of the project using one of the diagramming methods
Q3. Which of the following is NOT a tool for Perform Qualitative Risk Analysis Process?
Options:
A. Probability and Impact Matrix
B. SWOT (Strength, Weakness, Opportunities and Threat)
C. Monte Carlo Simulation
D. Root cause identification
Q4. You are managing a construction project . You have to decide between renting a digger or buying it for the project. You would require the digger for 7 days of work and following are the costs involved. Cost of digger is $1,400, daily cost of operation = $50, Daily rental of the digger= $250
Which of the following is true?
A. It is more economical to buy the digger
B. It is more economical to take the digger on rent
C. Both are equally economical
D. Can’t determine with the limited data
Q5.You are a project manager managing a challenging project in petrochemical industry. This project has high risk of personal injury to the members on the field. Where would you classify such Risks?
A. Business Risk
B. Pure Risk
C. Known Risk
D. Unknown Risk


aaron
Fri, 08/05/2011 - 16:37
Permalink
Q1) A. You can not go to
Q1) A. You can not go to Cost estimation until you have decomposed WBS into activities.
Q2) B. Choices A & D have already been done. Choice C is an output of the develop schedule process. Correct answer is B
Q3) Answer is C. Simulation is a technique for Quatitative risk analysis.
Q4) Answer is C. 1400 + 3*50 is same as 250 * 7
Q5) Answer is B. The only outcome is -ve in this case.
Do let me know the correct answers from the website. I have my exam scheduled for 8th Aug. It will be good to know where I stand :- )
nidhitripathi
Fri, 08/05/2011 - 18:11
Permalink
I believe the following are
I believe the following are the answers
1 - d
2 - b
3 - c
4 - c
5 - b
Please let me know the correct answers.
Thanks
Nidhi
working_hard
Sat, 08/06/2011 - 07:19
Permalink
Answers
SimpliLearn answers: d, c, c, c, b
sorry for the lengthy post.
Q1: SimpliLearn: Answer (d) All of the above. WBS provides deliverable oriented decomposition of work to be executed by project team to accomplish project objectives. And hence Work breakdown structure (WBS) is the primary input to all of the above process. It helps to identify specific actions to be performed to produce project deliverables (Define Activity), estimate cost for each activity within work package (Estimate Cost) and aggregate the cost estimates within work package to obtain Cost Budget (Determine Budget). For more details please refer to PMBOK 4th edition Project Time and Cost Management chapters PN 133 169,175.
My answer A - With out an activity list you cannot determine costs or budget. I dont get their answer.
Q2: SimpliLearn: Answer (c) Use this approved schedule as baseline and start tracking the project. The project manager is in the process develop schedule and since he has already derived an approved project schedule, it implies option (a) ,(b) and (d) are already completed as part of the processes Estimate Activity Resources, Develop Schedule and Sequence Activities. The next step would be to treat this estimate as schedule baseline and start tracking the project as part of process Control Schedule
My answer B - I am stumped and also this is a poorly worded question. A PM cannot create an approved project schedule, he/she would rather create a project schedule and then obtain approval.
Q3: SimpliLink: Answer (c) Monte Carlo Simulation. Monte Carlo Simulations are typically associated with Quantitative Risk Analysis Process. It generates the output as a range instead of a fixed value and shows how likely the output value is to occur in the range. For this purpose Monte Carlo Simulations allows several inputs to be used at the same time to create the probability distribution of one or more outputs. Some of the popular probability distribution used are Normal/Gaussian Distribution, Lognormal Distribution, Triangular Distribution and Uniform Distribution.
My answer: B - actually could by ( b or c or d)
Probability and Impact Matrix - Tool for Qualitative Risk Analysis
SWOT - Tool for Identify Risks
Monte Carlo Simulation - Tool for Quantitative Risk Analysis
Root Cause Analysis - Tool for Identify Risks (Risk information Gathering)
Q4: SimpliLearn: Answer (c) Both are equally economical . Please check the calculations for deriving the answer .Cost of digger is $1,400, daily cost of operation = $50, Daily rental of the digger= $250. If D is the number of days in which the cost of buying a digger equals cost of renting it . $ 250 D = $ 1400+$ 50D ; $ 200D = $ 1400 ; D = 1400/200 = 7 days. Since in 7 days the rental cost will be same as purchase cost and the project manager also requires it for exactly 7 its immaterial for him to rent or buy as far as cost is concerned.
My answer A; my thinking is that the cost of operations will exist in both the scenarios. An analogy would be; you have to spend money on gas whether you own a car or rent a car, which will lead us to the following calculations:
Buy: $1400 + $350 = $1750
vs
Rent: (7 x $250) + $350 = $2100
Q5: SimpliLearn: Answer (b) Pure Risk. This is an example of Pure risk or Insurable risk in the project which only offers an opportunity for loss unlike a business risk which provides an opportunity for gain as well as loss. Some other examples of pure risk in a project are fire, theft, hurricane etc
My answer: C - I did not know what was a "pure risk" at that time.
I would like to know if my thought process wrt to these questions is correct or not.
working_hard
Wed, 08/10/2011 - 01:28
Permalink
Question 4
Could someone please give me some explanation for Question 4?
fwdkhan1
Wed, 08/10/2011 - 10:05
Permalink
Correct answer of Q 1 is (A)
Correct answer of Q 1 is (A) You cannot Estimate Cost without Project Schedule. Page 167 PMBOK
aaron
Wed, 08/10/2011 - 17:03
Permalink
Daily cost of operation is
Q4. Daily cost of operation is paid only when you own the asset. For rental/leased assets it is not included e.g. the property tax and insurance premiums on rental property are not the responsibility of the person who rented. They are paid by the real owner of the asset and are already a part of the rent.
You can probably assume that the daily cost in this question is only the Fixed Cost (Insurance, Tax etc)
The variable cost (fuel required to operate the asset) seems to be ignored in these questions. (atleast should be ignored for the exam)
Kaam_wali_Bai
Wed, 10/12/2011 - 17:26
Permalink
I just completed 200
I just completed 200 questions from this site - Simplilearn and scored 70%. I wasn;t very impressed with quality of this site's questions. For example:
Question: Which of the following is the correct order of actions that you take during the closing processes?
Options:
A. Get formal acceptance, release the team, write lessons learned, close the contract
B. Write lessons learned, release the team, get formal acceptance, close the contract
C. Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract
D. Get formal acceptance, close the contract, write lessons learned, release the team
Explanation : Answer (c) Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract. One important fact is that you need your team’s help when you’re writing the lessons learned. That’s why you can’t release the team until the lessons learned are documented and added to the organizational process assets. Also, the last thing you do on the project is close the contract. Remember, release the project team is no longer part of closing as per the new RDS study conducted by PMI.
Your Answer : D Get formal acceptance, close the contract, write lessons learned, release the team
WHAT? " Remember, release the project team is no longer part of closing as per the new RDS study conducted by PMI." ? Which RDS study PMI did? Last time when I checked Deepfriedbrain and Rita', D is still valid.
I am scheduled for 17th. Studying PMstudy, Rita FasTrack & Oliver, Any other quality question paper site?