Your bank is launching an advertisement campaign for a new product. You have been instructed by the project sponsor to complete some milestones with the available skilled resources. From a project management perspective, this is:
1.
Constraint
2.
Assumption
3.
Discretionary dependency
4.
Mandatory dependency
Forums:


san
Fri, 05/24/2013 - 15:02
Permalink
Constriants. As per PMbok
Constriants. As per PMbok ,Constraints are delivery dates,policies , available skill resources (169 page)
vijayavadrevu
Fri, 05/24/2013 - 17:52
Permalink
Yes, constraints is the
Yes, constraints is the right answer. It is available in page 148 of PMBOK under Inputs of Estimate Activity Durations (also)
sanskrit
Sat, 05/25/2013 - 04:58
Permalink
1 constraints
1 constraints