Submitted by alfeldman on Tue, 07/23/2013 - 10:42
Hi
this is question in Cost section of Rita's book for CAMP. the answer is mark as "D" but i think it should be "A". Can you please confirm it?
Question: if the team is using performance measurement analysis and variance analysis, they are performing:
a) cost control
b) qualitative risk analysis
c) dependency determination
d) cost budgeting
Thanks
Al
Forums:


yasser
Fri, 05/22/2015 - 17:40
Permalink
A
Aslong he mentioned variance this meaning something related to monitoring and controlling