Cost Formula Difference
Submitted by mickcalcara on Tue, 05/18/2010 - 17:45
Hi, I notice Estimate at Completion formula difference.
In Rita Mulcahy book ( pg 242 ) a variation of EAC is listed as:
‘AC+[(BAC-EV)/(Cumulative CPI + Cumulative SPI)]
In PMBOK (Pg. 185 ) this is listed as:
‘AC+[(BAC-EV)/(Cumulative CPI * Cumulative SPI)]
I assume the PMBOK formula is the most accurate. Can someone verify this?
Thanks
Forums:


biswasrahul
Tue, 05/18/2010 - 18:03
Permalink
AC+[(BAC-EV)/(Cumulative CPI
AC+[(BAC-EV)/(Cumulative CPI * Cumulative SPI)] is the correct formula
The PMP Guru
Tue, 05/18/2010 - 18:55
Permalink
Cost Formula Difference
RITA Corrected this in her new Errata sheet on her site.
There are also some other small mistakes that's in the First Ver of the Sixth Edition has been higlighted in the errata.
Kind regards,
The PMP Guru.