Hi All:


 


If a project is over, how come its SPI and CPI or CV and SV would be at least 1.


 


 


 


I am not understnading it. Can it be explained please.


 


Thanks,


KK

SPI and SV has to do with schedule and CPI and CV is associated with the cost. You can have any values (<1 or >1) of these at any project phases depending upon the project status. Hence, look at the scenario that’s given and not its number to decide the project phase.