Float question from time management

The earliest Task C can finish is January 21, and the earliest the next task can start is January 28. From this information we can be sure that:


A.  Task C has 6 days of float
B.  Task C has 6 days of free float
C.  Task C has 7 days of free float
D.  Task C has 7 days of float

 

Please also briefly explain the choice.

Thank you all.

0
Your rating: None

Answer is C

Free Float is the amount of time activity (C) can be delayed without delaying the early start date of next task.

or Free Float= Early start date of successor activity- Early start date of precessedor activity

Free Float= 28-21=7.

You can follow the below link for more details regarding free float

http://www.deepfriedbrainpmp.com/2009/08/total-free-float-cpm-network-diagram.html

 

 

Answer is B

Float of 'C' = Earliest start of Subsequent task-Earliest Finish of C - 1

               = 28-21-1= 6 days

By Jan. 27, C must be finished so next Activity 'D' can start on Jan. 28.    Even if you look at : Float = LF-EF= 27-21=6 days is the maximum relaxing period you get.

Another way to look at is: You can finish as early as Jan. 21.  So Jan 22, 23, 24, 25, 26, 27 ( 6 days) are your spare days without causing delay to start the next activity on Jan. 28.

 

Chandra

Float question from time management

Chandra, Your answer is right.

 

Even i made a mistake picking 7 days of free float.

6 Days free float is right.

 

Thank you for the explanation.

 

 