***Management Plan Question**
Submitted by sam_jain on Sun, 05/13/2012 - 21:31
| Question: A major stakeholder in the project wants to know his role and responsibility in the scheduling process of the project. He also wants to understand how the schedule baseline is established for the project and which scheduling methodologies are used in the project. Which document should the project manager ask him to refer to? |
| Options: |
| A. Project Management Plan |
| B. Project Schedule Baseline |
| C. Stakeholder Register |
| D. Schedule Management Plan |
Correct Answer : D
My Question : Whether Schedule Managment Plan talks about Roles and Responsibility ( it could be in Estimate Activity resouces). But typically it comes under HR Management Kknowledge Area.
My answer is A
Please advise .....
Regards..Sam
Forums:


admin
Mon, 05/14/2012 - 05:16
Permalink
Slightly ambigous question.
Slightly ambigous question. But since this is all about schedule mgmt, it can be found in schedule management plan.
diba_perfect
Mon, 05/14/2012 - 08:20
Permalink
agree..but isn't the Schedule
agree..but isn't the Schedule Management Plan a component of the overall PM Plan?
projmanpro
Mon, 05/14/2012 - 11:53
Permalink
it is contained in the Proj
it is contained in the Proj Mgt Plan, but the question is specifically refering to sched mgt plan. In other words, if i ask you a yellow-coloured crayon, are u going to give me the crayon box and just let me select the specific yellow crayon i want? :)
As Admin pointed out, the question was made tricky by the first sentence, however, it does not make the question wrong. The stakeholder in this situation could be assumed to be not knowledgeable of his roles and responsibilities - but specifically related to scheduling. Then the required of the question is best stated in the proceeding sentence.
Schedule Management Plan sets the format and criteria in developing and controlling the project schedule.
saket_pmp
Mon, 05/14/2012 - 12:27
Permalink
I would choose “Project Management Plan”
Friends, this one is interesting, if I decompose this question I would see three units of information that the major stakeholder in the project wants to know:
1. Role and responsibility
2. Schedule baseline
3. Scheduling methodologies
I would rather choose “Project Management Plan” since this is the only and best place where you can get everything i.e. it has contents from output of all planning process.
kumark
Thu, 11/08/2012 - 13:39
Permalink
RBS is o/p of Activity resource
if it is confusion around R&R then I think RBS (Resource Breakdown Structure) is o/p of estimate Activity resourcea and contains not only skilled labour but also material, equipment etc.
thanks
Kapil