Qus1.All of the following statements are true regarding the Develop Human Resource Plan process except for which one?
-
The Develop Human Resource Plan process involves determining roles and responsibilities.
-
Included in the Develop Human Resource Plan output are project organization charts that show the project's reporting relationships.
-
The staffing management plan created in this process describes how and when resources will be acquired and released.
-
A RAM (or RACI chart) is an output of this process that allows you to see all the people assigned to an activity.
Qus2: The quality management plan documents how the project team will implement the quality policy. It must address at least all of the followingexcept which one?
-
Quality control
-
Quality metrics
-
Quality assurance
-
Continuous process improvement


sspawar
Thu, 10/11/2012 - 23:52
Permalink
level of questions are
level of questions are low.
that why you are confusing
any way what answer is provided is based on that
1.D is a general thought, not been universally true. as all people on an activity is not possible within RACI
2,Quality Metrics is the part of quality plan process, so its not necessary to address separately.
tmanivannan
Fri, 10/12/2012 - 01:48
Permalink
Thanks for your comments. I
Thanks for your comments. I have takenthem from Kim Heldman book (Chapter6).
- Mani
anand_kl
Fri, 10/12/2012 - 12:17
Permalink
My answer is....
Dear Mani,
Answer to Q 1 :
Correct answer is D. Please understand that T&T and Output has a difference here:
(Tip: You might have seen Orgainzation chart as a Tool in Microsoft powerpoint slides. These can be used to show any hirearchy, may be it of your project team structure, your Business unit reporting strucutre, the whole organization reporting strucutre ...etc)
Answer to Q 2: I agree with SS Pawar
Regards,