Need help-Procurement Management
Submitted by wsu on Wed, 03/04/2015 - 02:15
1. During which procurement processes does procurement negotiation occur?
a. Plan Procurement Management and Close Procurements
b. Control Procurements and Close Procurements
c. Conduct Procurements and Control Procurements
d. Conduct Procurements and Close Procurements
Forums:


sun360
Wed, 03/04/2015 - 02:22
Permalink
D. Both processes use
D. Both processes use procurement negotiations.
wsu
Wed, 03/04/2015 - 02:34
Permalink
Do they occur during both?
But do they occur during both?
coolpmp69
Wed, 03/04/2015 - 13:52
Permalink
Correct option is D- Conduct
Correct option is D- Conduct Procurements and Close Procurements
In Conduct Procurements - PM or procurement manager negotiates contract price and scope with the seller
In close procurement - PM negotiates claims if any before closing it.