Need help-Procurement Management

 

1.     During which procurement processes does procurement negotiation occur?

a.     Plan Procurement Management and Close Procurements

b.    Control Procurements and Close Procurements

c.     Conduct Procurements and Control Procurements

d.    Conduct Procurements and Close Procurements

D. Both processes use procurement negotiations.

But do they occur during both?

Correct option is D- Conduct Procurements and Close Procurements

In Conduct Procurements - PM or procurement manager negotiates contract price and scope with the seller
In close procurement - PM negotiates claims if any before closing it.