Dependency questoins
Submitted by Jgrind07 on Mon, 05/06/2013 - 20:42
A technical team can begin editing of a large document 15 days after they begin writing it. What kind of a dependency would this be represented as?
-
Start-to-start with a 15-day lead -
Finish-to-finish with a 15-day lead -
Start-to-start with a 15-day lag -
Finish-to-start with a 15-day lag
What the correct answer? You explainatin please.
Thanks
Jai
Forums:


crushPMP
Mon, 05/06/2013 - 21:51
Permalink
Seems to me like a SS
Seems to me like a SS relationship with a 15 day lag - C
Jgrind07
Mon, 05/06/2013 - 23:03
Permalink
Your correct, CrushPMP.I
Your correct, CrushPMP.
I thought the document must be finished to start to edit it and so selected FS which was wrong. What is your justification to your choice?
Thanks
Jai
crushPMP
Mon, 05/06/2013 - 23:13
Permalink
Jai - The keywords here are
Jai - The keywords here are "begin editing" and "begin writing" which tells me that there is a SS relationship of some kind between the 2 activities.
Jgrind07
Mon, 05/06/2013 - 23:23
Permalink
Got it, Thanks CrushPMP
Got it, Thanks CrushPMP