Developing alternative activity sequence

Developing alternative activity sequence exemplifies

A)Risk aversion

B)Workaround

C)Rolling wave

D)Contingency planning

 

 

cnppmp's picture

D? for soemthing fails after risk response planning you have contingency plan to look at>


Regards


CN Patil

You are right. I have chosen the option, Workaround. Can you please elaborate as to why work around is not correct and contingency plan is right?

 D i.e. Contingency planning

 

Work around is what you do when a unidentified / unknown risk occures, It's not PLANNED risk response

Yes I understand. Thank You