Stakeholder Register or Stakeholder Management Strategy ?
Submitted by bridge on Thu, 06/27/2013 - 03:33
The project is in early stage. You know that the stakeholders are very influential and firm about their requirements. You record this as part of ?
A. Stakeholder Register
B. Stakeholder Management Strategy
C. Communication Management Plan
D. Project Management Plan.
PMPForSure Answer : B
BUT -
PMBOK Page 250 - 10.1.3 - Assessment Information under Stakeholder Register : "Major requirements, main expectations, potential influence in the project, phase in the life cycle with the most interest..."
What is correct ?