Opportunity Cost

 

Which of the following projects described below will you select? 
 
 
  Choice 1 Project A with opportunity cost of $ 100,000 and investment of $ 1,000,000.
 
  Choice 2 Project B with opportunity cost of $ 200,000 and investment of $ 500,000.
 
  Choice 3 Project C with opportunity cost of $ 300,000 and investment of $ 3,500,000.
 
  Choice 4 Cannot be determined from the above options.

We don't know anything else apart from investment - so based on opportunity cost I will go with choice 1 - the one with less OC .

 

Choice 4.

 

Regards.

 

cnppmp1's picture

always low opportunity cost to be selected..and it is A, which has $100,000


Regards


CN Patil

 choice 4 as enough info is not present

Project are selected based on investment. Opportunity cost is project cost that you give up and it just project $ value you won't be doing. Project selection is based on the factors of investment, which is not clear here so would go for option 4.  

As per test authors Correct answer was 4