Question No : 133
 
  As a project manager, you understand the importance of identifying and documenting project risks. In this context, which of the following statements is true?
 
 
  Choice 1 Risk identification occurs during the Planning of the project
 
  Choice 2 Risk identification occurs during Monitoring and Controlling of the project
 
  Choice 3 Risk identification occurs during Execution of the project
 
  Choice 4 Risk identification occurs during different project stages depending on the type of the project
 
 
  Correct Choice : 1
 
  Justification : 
 
  Risk identification is done as part of the Planning Process Group

 

 

As I remeber, Rita's book says that Risks may be identified within whole project life cycle, not only planning. Have I missed something? Please advise

 Choice 1 : Is the only one thats is correct among the AVAILABLE option

I think your question is why not Choice 4 ?

The way I will explain the reason choice 4 is wrong is risk identification process group does NOT depends on the type of the project.