Question - Quality Management
You have just reviewed the most recent audit from the quality assurance organization which has identified an out-of-control process. You call the members of the technical team in for an emergency meeting to address the situation, as this is a critical process in your development effort. Analyzing an out of control situation for remediation occurs in which process and results in the creation of?
a. Perform quality assurance and project management plan updates
b. Perform quality control and change requests
c. Perform quality assurance and change requests
d. Perform quality control and validated changes


admin
Fri, 09/24/2010 - 08:06
Permalink
The answer choices are not
The answer choices are not good , but B is my answer
raj9
Sun, 10/03/2010 - 17:33
Permalink
Answer
Quality audit is T & T of perform quality assurance process.
Project management plan updates includes change request. Hence correct answer is - choice A.
Raj
NowAPMPDude
Thu, 10/07/2010 - 23:47
Permalink
Correct Answer
It's C. It's talking about "process", that alone tells you it's just A or C. You can eliminate "quality control". And since this is talking about results, the process of reporting any kind of discrepancy is "change request".
See, this is an easy 1. Good luck!
PMP King
Tue, 10/19/2010 - 09:20
Permalink
Question - Quality Management
Good question.
Analysing out of control process falles under Perform Quality control process. It results in Change request as well as in validated changes. So answer B and D can be right. The question suggests still there is no recommendation for changes as problem is still to be identified. Hence B is right choice than D.
mgurunath
Tue, 10/19/2010 - 12:05
Permalink
I agree with the KING :)B
I agree with the KING :)
B would be my take.
krantikumar50
Tue, 07/10/2012 - 07:24
Permalink
I would go with
The answer is "C"... Quality auditing is done in Perform QA process....
KK...
sspawar
Tue, 07/10/2012 - 15:42
Permalink
your logic is true
But, question is on situation after auditing activity is over
QA team has gone submitting his report, you are now reviewing and analysing and trying for a remady (contol).
Its my view.
krantikumar50
Tue, 07/10/2012 - 15:49
Permalink
Now
Now, I have the answer since it comes from the legend respected Pawarji Sir.
When is remady done in Quality management Sir? Remady is the output or input of which PQM process respected Pawarji Sir? Precisely what is remady?
Warmly, KK...
sspawar
Tue, 07/10/2012 - 21:15
Permalink
here control - means remedy - also change
Analyzing an out of control situation for remediation occurs in which process and results in the creation of?
here control - means remedy - also change
jackson88
Tue, 07/10/2012 - 07:19
Permalink
Inspection
Electrospec's excellent examination procedure uses the IDEA-STD-1010-A standard as a basis for their extensive qc.A top excellent examination procedure quality inspection service would include several different factors including certified qc personnel.