Question - Quality Management

You have just reviewed the most recent audit from the quality assurance organization which has identified an out-of-control process. You call the members of the technical team in for an emergency meeting to address the situation, as this is a critical process in your development effort. Analyzing an out of control situation for remediation occurs in which process and results in the creation of?


a. Perform quality assurance and project management plan updates
b. Perform quality control and change requests 
c. Perform quality assurance and change requests


d. Perform quality control and validated changes

admin's picture

The answer choices are not good , but B is my answer

Quality audit is T & T of perform quality assurance process.


 


Project management plan updates includes change request. Hence correct answer is -  choice A.


 


Raj

 It's C.  It's talking about "process", that alone tells you it's just A or C.  You can eliminate "quality control".  And since this is talking about results, the process of reporting any kind of discrepancy is "change request".  

See, this is an easy 1.  Good luck!

Good question.


Analysing out of control process falles under Perform Quality control process. It results in Change request as well as in validated changes. So answer B and D can be right. The question suggests still there is no recommendation for changes as problem is still to be identified. Hence B is right choice than D.

 I agree with the KING :)

B would be my take.

The answer is "C"... Quality auditing is done in Perform QA process....


 


KK...

But, question is  on situation after auditing activity is over

QA team has gone submitting his report, you are now reviewing and analysing and trying for a remady (contol).

Its my view.

Now, I have the answer since it comes from the legend respected Pawarji Sir.


 


When is remady done in Quality management Sir? Remady is the output or input of which PQM process respected Pawarji Sir? Precisely what is remady?


 


Warmly, KK...

Analyzing an out of control situation for remediation occurs in which process and results in the creation of?

here control - means remedy - also change