Question - Quality Management
You have just reviewed the most recent audit from the quality assurance organization which has identified an out-of-control process. You call the members of the technical team in for an emergency meeting to address the situation, as this is a critical process in your development effort. Analyzing an out of control situation for remediation occurs in which process and results in the creation of?
a. Perform quality assurance and project management plan updates
b. Perform quality control and change requests
c. Perform quality assurance and change requests
d. Perform quality control and validated changes


The answer choices are not
The answer choices are not good , but B is my answer
Answer
Quality audit is T & T of perform quality assurance process.
Project management plan updates includes change request. Hence correct answer is - choice A.
Raj
Correct Answer
It's C. It's talking about "process", that alone tells you it's just A or C. You can eliminate "quality control". And since this is talking about results, the process of reporting any kind of discrepancy is "change request".
See, this is an easy 1. Good luck!
Question - Quality Management
Good question.
Analysing out of control process falles under Perform Quality control process. It results in Change request as well as in validated changes. So answer B and D can be right. The question suggests still there is no recommendation for changes as problem is still to be identified. Hence B is right choice than D.
I agree with the KING :)B
I agree with the KING :)
B would be my take.