question in risk management knowledge area
Submitted by vijayavadrevu on Sat, 03/16/2013 - 04:52
The question is: Management has just assigned you to an important new project and you need to figure out the path convergence in the figure shown, if the odds of completing activities 1, 2 and 3 on time are 50%, 30% and 40%. What are the chances of starting activity 4 on day 6??
Regards
Vijaya
Forums:


sspawar
Sat, 03/16/2013 - 06:47
Permalink
It should be like this
It should be like this :=0.50*0.40*0.30 = 0.06
50%
ACTIVITY
1/ 5DAYS
>
30%
6%
START
ACTIVITY
2/ 5DAYS
ACTIVITY 4
>
>
>
40%
ACTIVITY
3/ 5DAYS
>
vijayavadrevu
Sat, 03/16/2013 - 07:03
Permalink
Thank You Sir
Thank You Sir