Risk response plan for secondary risk

 Hi all ,

 

How do we handle secondary risk? Shall we use contingency plan for that? 

 

Regards

 

abdsal

Secondary Risk is basically an accepted risk after the risk response which is tolerable to the Organization.


However in case of secondary risk becomes intolerable and significant, then fall back plan has to be resorted from the Contingency allocated for such activity


 

 

 

Dear thakkar,

 

thank you!!!

 

abdsal

Secondary risk is a new risk emerged out of any risk response plan implementation.

Shouldn't it be treated iteratively into risk analysis processes and develop a response for it?

We have "contingency plans", if it fails "fallback plans" made for residual risks (actively accepted)

Pls correct me if am wrong

 11.5.2 is indicating for response review.