Stakeholder Register or Stakeholder Management Strategy ?

The project is in early stage. You know that the stakeholders are very influential and firm about their requirements. You record this as part of ?

 

A.  Stakeholder Register

B. Stakeholder Management Strategy

C.  Communication Management Plan

D.  Project Management Plan.

 

PMPForSure Answer : B

BUT -

PMBOK Page 250 - 10.1.3 - Assessment Information under Stakeholder Register : "Major requirements, main expectations, potential influence in the project, phase in the life cycle with the most interest..."

 

What is correct ?