help with this question pls
Submitted by abiodun.lm@gmail.com on Fri, 07/12/2013 - 19:47
In shortening the project duration,the first action to take is to
A) Change the project scope
B) Crash as many activities as possible
c) Fast-track activities on critical path
D) cuonsume the float on critical path
I know its seems simple but there is a confusion please what is the corect answer and please with a little explanation.