document capturing impact of delay
Submitted by vijayavadrevu on Mon, 05/06/2013 - 16:09
Forums:
You are a project manager managing a construction project which is midway through the execution phase. The project is progressing well and is on time when one of the vendors informs you that a weeklong delay in his shipment delivery due to a law and order problem in his city. Which of the documents would best capture the impact of the delay on the project?