PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

organization structure -- type

 You are managing a complex project which requires some highly skilled resources on embedded design. You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you need to free these resources for reassignment. You are working in which kind of organization structure?

Pages