Dependency questoins
Submitted by Jgrind07 on Mon, 05/06/2013 - 20:42
Forums:
A technical team can begin editing of a large document 15 days after they begin writing it. What kind of a dependency would this be represented as?
-
Start-to-start with a 15-day lead