risk response

As a project manager, you have called for a risk review meeting. While going through the risk register, you found out that there is a risk, which still exists, even after applying all risk response strategies. What would you do?

A)This is a residual risk. Look for another set of response strategies

B)Re-calculate Risk Probability * Impact Value