risk response
Submitted by vijayavadrevu on Mon, 05/06/2013 - 10:42
Forums:
As a project manager, you have called for a risk review meeting. While going through the risk register, you found out that there is a risk, which still exists, even after applying all risk response strategies. What would you do?
A)This is a residual risk. Look for another set of response strategies
B)Re-calculate Risk Probability * Impact Value