Change Request Question
Submitted by sanskrit on Sat, 05/04/2013 - 17:59
Forums:
In the 5th Month of 1 Year project, Project Manger recognizes that the team is not progressing as fast as planned, and will likely be a week or two late with the project. He has tried to compress the schedule, and has considered reducing scope. At this point, it seems there is no way to finish any earlier. Which of the following actions should Anand take?