Earned Value interpretation
Q24. You have calculated Earned Value measures and report them to your stakeholders. BAC = 20,000; PV = 18,600; EV = 17,500; AC= 17,000; CPI=1.03; SPI=0.94; EAC= 19.400. What do these figures tell you about the project performance to date?
A. The budget at completion is less than estimate at completion
B. You are ahead of schedule
C. The estimate at completion is over the original budget
D.The cost performance index tells us that we are getting a good return for the money spent on the project so far