Risk Management Question
Submitted by siddus on Thu, 05/02/2013 - 11:29
Forums:
A project manager has assembled the project team, idenhfied 56 risks on the project, determined
what would trigger the risks, rated them on a risk rating matrix, tested their assumptions,
and assessed the quality of the data used. The team is continuing to move through the risk
management process. What has the project manager forgotten to do?
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involvement of other stakeholders
D. Involvement of other stakeholders