PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Risk Management Question

A project manager has assembled the project team, idenhfied 56 risks on the project, determined
what would trigger the risks, rated them on a risk rating matrix, tested their assumptions,
and assessed the quality of the data used. The team is continuing to move through the risk
management process. What has the project manager forgotten to do?
 
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involvement of other stakeholders
 