EAC Calculation Question
Please help me to calculate the EAC
As a project manager, you are required to produce project performance reports on a regular basis, your project`s Budget at Completion is $750,000, planned value is $100,000, schedule variance is $30,000, and cost variance is $50,000. What is the percentage complete and estimate at completion in your project?
Choice 1 18%, $ 500,000
Choice 2 17.33%, $ 461,538
Choice 3 17.8%, $ 437,500
Choice 4 18%, $ 437,500