PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Rita question - What is discussed in every team meeting?

Which of the following MUST be an agenda item at all team meetings?

A. Discussion of project risks

B. Status of current activities

C. Identification of new activities

D. Review of project problems

 

My answer and correct answer are below:

 

 

 

 

 

 

My answer: B

Correct answer: A

 