TCPI Calculation
Submitted by Jgrind07 on Thu, 05/02/2013 - 03:21
Forums:
Please help me in calculating the TCPI
For your project, find the to-complete performance index (TCPI) based on the given data:
Budget at completion of the project = 700,000
Cost variance of the project = 25,000
Earned value of the project = 200,000
Estimate to Complete has now been revised to 425,000
Choice 1 0.9
Choice 2 1.176
Choice 3 1.5
Choice 4 -1.5
Thanks
Jai