Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

duration and schedule problem

 Activity A = 4days, B = 3 days, C=7days, D=5days and E=3days. A is predecessor of B and C, E is successor of B and D, C is predecessor of D. There is a lag of 3 days between C and D. There are 2 non working days.What do you see from this data?

A) Duration is 22 days

B)Schedule is 19 days

C) Duration is 24 days and schedule is 22 days

D)Duration is 22 days and schedule is 24 days

 

Answer is D

 

Can someone explain as to how to solve this problem?