PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Plan Procurements / Define Scope


You are a project manager at a construction company. You have to plan when to obtain the products and services from the vendors. In which of the following process this should be determined?
Answers :  
 A)Estimate Activity cost
 B)Plan Procurements
 C)Define Scope
 D)Define activities

Ans is C.

Please provide clarification . I am thinking that option B is correct.