question from Rita Mulcachy

This is a question from Rita Mulcachy: 

A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to complete work packages. What should the new project manager do NEXT?

A. Coordinate completion of work packages.

B. Identify quality standards.

C. Begin the Identify Risks process.