Sequencing method
Submitted by san on Thu, 04/25/2013 - 04:53
Forums:
Jack is working with his project team to develop a network diagram, and noticed that a series of activities can go in parallel but must end in a specific sequence. What type of activity sequencing method should be used?
Answers :
1)Precedence diagramming method
2)Arrow diagramming method
3)Critical path method
4)All of the above
Which one to choose between 2 and 3