Sequencing method

  
Jack is working with his project team to develop a network diagram, and noticed that a series of activities can go in parallel but must end in a specific sequence. What type of activity sequencing method should be used?
Answers :  
 1)Precedence diagramming method
 2)Arrow diagramming method
 3)Critical path method
 4)All of the above